Stucco Manufacturing Plant to produce "One Coat" stucco
French Camp, CA |
|
Guntert & Zimmerman Const. Div., Inc. |
|
Guntert & Zimmerman Const. Div., Inc. |
|
Hawn Engineering |
|
Kleinfelder, Inc. |
|
Guntert & Zimmerman Const. Div., Inc. |
|
Guntert & Zimmerman Const. Div., Inc. |
|
Kraemer & Co. |
|
Agri Electric |
|
Granite Construction Co. |
| |
|
|
|
|
Turnkey project duration from permit application to open house, including design & engineering, 180 days
|
|
|
|
|
|
|
Structural steelwork in erection stage
|
|
| |
|
|
|
|
Fully computerized and automatic batching system with bagging operation
|
One of three 120 ton, two compartment silos under construction at G&Z Plant
|
|